Follow the Progress
of Our New Addition in Photos!
December 13, 2007 - Foundation
being backfilled
 |
December 21, 2007 - Slab poured
and Partial Framing
 |
- December 27, 2007
- Weather and Christmas holiday delays, but some progress!
 |
- January 4, 2008 -
Progress! First floor framed and sheathed.
 |
- January 10, 2008
- All sheated, roof
on, almost all closed in!
 |
 |
 |
- January 17, 2008
- Windows in, Tyvek
on
 |
 |
 |
- January 23, 2008
- All closed in! HVAC
and electrical underway ...
 |
 |
- January 31, 2008
- Exterior clapboard
on, HVAC and insulation in and keeping addition warm, wallboard
going up!
 |
 |
- February 7, 2008
- Taping almost complete!
 |
- February 15, 2008
- Taping Complete!
 |
 |
- February 29, 2008
- Painting!
 |
 |
- March 18, 2008
- Electrical complete;
wall to existing building opened
 |
- © 2008 LEWISBORO
VOLUNTEER AMBULANCE CORPS
- ALL TEXT AND PHOTOGRAPHS
ARE THE PROPERTY OF THE LEWISBORO VOLUNTEER AMBULANCE CORPS
- AND MAY NOT BE REPRODUCED
WITHOUT WRITTEN PERMISSION.
- ALL RIGHTS RESERVED.